Version
gururao.1976@... 9th Jul 2008
What is the Version of MS Excel should be installed in the System.
0 Votes
+ -
Any version
kbashir@... 9th Jul 2008
I don't think in this case Excel version have any issue. As long the version you have supports Network days the formula will work.
0 Votes
+ -
Add-In
bobwright@... 20th Jul 2008
If this function is not available, and returns the #NAME? error, install and load the Analysis ToolPak add-in.

How?

On the Tools menu, click Add-Ins.
In the Add-Ins available list, select the Analysis ToolPak box, and then click OK.
If necessary, follow the instructions in the setup program.
0 Votes
+ -
I think you meant shift+down arrow. ctrl+shift+down arrow does weird things. thanks for the tip.
This is really cool I gave it a try and it worked out for me.Thanks for the article its a wonderful way to track the progress of my project.
Thank you
Blessing
www.xpertva.com
Can you use or know how to do this same function with a Sharepoint list?
0 Votes
+ -
VBA
ksawaneh@... 31st Jul 2008
Hai,
can some one help me, a guideline to write VBA.
Introduction
0 Votes
+ -
Calculate remaining days
kloefgren@... Updated - 18th Jan 2009
If you replace the date in the "start date" cell with the TODAY( )function, the spreadsheet will calculate the current number of work days remaining to the "end date".
Thanks for this function. I seem to be brain-dead on ideas: can you use this to calculate the DATE after a certain number of working days? I have a start date and need to calculate the due (end) date for the project report based on 10 working days.
Thanks for this function. I seem to be brain-dead on ideas: can you use this to calculate the DATE after a certain number of working days? I have a start date and need to calculate the due (end) date for the project report based on 10 working days.
0 Votes
+ -
=WORKDAY(StartDate,NumberOfWorkDays,ListOfHolidays)
This techneque is to count the number of working days., Pl some one help to find a formula to skip the saturday, sunday and holidays between two task dates... eg start 1/9 end 1/31.. total 31days. need a formula that excel skip automaticall these days when calculating the days.
When making your list for Holidays simply follow that with all the weekend dates for the year. Then make sure the holiday dates and weekend dates are selected together. Use the formula provided in this example and it works! Please remember you might have to add the add in. Go to the help search and type in NETWORKDAYS where it will provide direction as to how to get the add in and other helpful hints. Really glad I found this on the web, saved me a ton of time!!!!!! THANK YOU!
0 Votes
+ -
Working days
ken@... 10th Jan 2012
The functions here will work up to 9999. Any extra bank holidays can be added in a similar manner to the 5th June Diamond jubilee one.
The EasterSunday function was not written by me but comes from the ERLANDSEN DATA CONSULTING site and is, I think, the sweetest bit of code I've seen.

Function EasterSunday(InputYear As Integer) As Long
' Returns the date for Easter Sunday, does not depend on Excel
Dim d As Integer
d = (((255 - 11 * (InputYear Mod 19)) - 21) Mod 30) + 21
EasterSunday = DateSerial(InputYear, 3, 1) + d + (d > 48) + 6 - _
((InputYear + InputYear \ 4 + d + (d > 48) + 1) Mod 7)
End Function


Function WrkDays(StartDate As Date, EndDate As Date) As Integer
Dim d&
Dim Cnt&
Dim DC As Date
Dim WD&
Dim A&
Dim M&
Dim NY&
Dim ES As Date
Dim EM&
Dim Yno
Dim DN&
Dim CD As Date
Dim BD As Date
'Dim ES As Date

'It is assumed that there will only be 1 easter during the spell
'Check for a weekend
d = EndDate - StartDate
DC = StartDate
A = 0
NY = 0
'Stop
For Cnt = 1 To d Step 1
WD = Weekday(DC, vbSunday)
DN = DatePart("d", DC)

Select Case WD
Case 1, 7
'This is a weekend
A = A
Case Else
'This is a weekday
'Check for a bank holiday
'Get the month from the date DC
M = Month(DC)
Select Case M
Case 1
'January
'NYD is first weekday
'Check the day number
'is the start date in the first week
'Find the day of January 1
CD = DateValue("1/1/" & Year(DC))
'What day of the week is it?
WD = Weekday(CD)
Select Case WD
Case 1
'Sunday
'nyd Tomorrow
If DC = CD + 1 Then
A = A
Else
A = A + 1
End If
Case 2, 3, 4, 5, 6
'Monday, Tuesday, Wednesday, Thursday or Friday
'NYD today
A = A
Case 7
'Saturday
'NYD Monday
If DC = CD + 2 Then
A = A
Else
A = A + 1
End If

End Select
Case 2
'February
'No current holidays
A = A + 1
Case 3
'March
'Earliest dates for Easter
'Get the date of easter
ES = EasterSunday(Year(DC))
EM = Month(ES)
If EM = M Then
'Easter is this month
If DC ES - 2 Then
A = A + 1
ElseIf DC ES + 1 Then
A = A + 1
End If
Else
A = A + 1
End If

Case 4
'April
'Late dates for Easter
'Get the date of easter
'Stop

ES = EasterSunday(Year(DC))
EM = Month(ES)
If EM = M Then
'Easter is this month
If DC = ES - 2 Then
A = A
GoTo ED
ElseIf DC = ES + 1 Then
A = A
GoTo ED
Else
A = A + 1
End If
Else
A = A + 1
End If
ED:
Case 5
'May
DN = DatePart("d", DC)
Select Case DN
Case 1 To 7
'First monday in May
Select Case WD
Case 2
'This is a Monday
Case Else
'The other days are working days
A = A + 1

End Select
Case 25 To 31
'Last Monday in May
Select Case WD
Case 2
'This is a Monday
Case Else
'The other days are working days
A = A + 1

End Select
Case Else
A = A + 1
End Select

Case 6
'June
'No Current Holidays
'Diamond Jubilee 2012 only 5th June
'is the year 2012?



'Specific code for extra bank holidays
'Select the year
Yno = Year(DC)
'Check if this year applies to the bank holiday
If Yno = 2012 Then
'If the year is relevant then do the following
DN = DatePart("d", DC)
'Get the day number
If DN 5 Then
'Check if the day number matches the day of the bank holiday
A = A + 1
'If it does not match add 1 to the working days total
End If
Else
A = A + 1
End If

Case 7
'July
'No Current holidays
A = A + 1
Case 8
'August
'Last Monday in August
DN = DatePart("d", DC)
Select Case DN
Case 25 To 31
'Last Monday in May
Select Case WD
Case 2
'This is a Monday
Case Else
'The other days are working days
A = A + 1

End Select
Case Else
A = A + 1
End Select

Case 9
'September
'No Current Holidays
A = A + 1
Case 10
'October
'No current Holidays
A = A + 1
Case 11
'November
'No Current Holidays
A = A + 1
Case 12
'December
'25th Christmas
'26th Boxing day
'If Christmas or Boxing day is a weekend then the next weekday is used.
Yno = Year(DC)
CD = DateValue("25/12/" & Year(DC))
BD = DateValue("26/12/" & Year(DC))
WD = Weekday(CD, vbSunday)
Select Case WD
Case 1, 7
'Christmas day is a Saturday or Sunday
'The following Monday and Tuesday are bank holidays
If WD = 1 Then
If DC = CD + 1 Then
A = A
ElseIf DC = CD + 2 Then
A = A
Else
A = A + 1
End If

ElseIf WD = 7 Then
If DC = CD + 2 Then
A = A
ElseIf DC = CD + 2 Then
A = A
Else
A = A + 1
End If

End If

Case 2, 3, 4
'Christmas day is a Monday, Tuesday, Wednesday or Thursday
'Today and Tomorrow are bank holidays
If DC = CD Then
A = A
ElseIf DC = CD + 1 Then
A = A
Else
A = A + 1
End If
Case 6
'Christmas day is a Friday
'Friday and the following Monday are bank holidays
If DC = CD Then
A = A
ElseIf DC = CD + 3 Then
A = A
Else
A = A + 1
End If

Case Else

A = A + 1
End Select


End Select
'A = A + 1
End Select
DC = DC + 1
Next Cnt
WrkDays = A

End Function
Keyboard Shortcuts:
Prev
Next
Toggle
Join the conversation
Formatting +
BB Codes - Note: HTML is not supported in forums
  • [b] Bold [/b]
  • [i] Italic [/i]
  • [u] Underline [/u]
  • [s] Strikethrough [/s]
  • [q] "Quote" [/q]
  • [ol][*] 1. Ordered List [/ol]
  • [ul][*] · Unordered List [/ul]
  • [pre] Preformat [/pre]
  • [quote] "Blockquote" [/quote]

Join the TechRepublic Community and join the conversation! Signing-up is free and quick, Do it now, we want to hear your opinion.