Planned baseline curve of earned value analysis to frequent project changes

Tags:
+
0 Votes
Locked

Planned baseline curve of earned value analysis to frequent project changes

Gina Laviste
Frequent changes to project schedule to accomodate progress or lag from activity completions affect your planned s-curve to your earned value analysis. Does this mean everytime the project team agrees to changes in schedule (which will affect resources), the planned s-curve also changes?

Does this mean that earned value calculations done in previous activities will also be recomputed?