I frequently perform a state assessment as the first phase in a project. I've found that it is most useful if I split the assessment into three areas:
- infrastructure (Hardware and network including server OS)
- applications (both off-the-shelf and custom)
- processes
The process is simple and flexible - there are several ways to collect the needed information. My standard process is:
1) Start with an org chart
2) Based on the org chart, put together a team that can give at least a skeleton structure of the business processes
2) Document infrastructure (inventory and network map)
3) Inventory the applications
4) Team meeting to define high-level view of processes (I try to match the applications to the processes in this meeting)
5) Follow-up with interviews, facilitated sessions, and following a process from start to finish.
My final documentation is structured into the same three sections. I include a high-level network map for servers and segments only. And I includeprocess diagrams where appropriate. I include an overall evaluation and recommendation, backed up by specific evaluations in each section.
Depending on the level of detail required this can be a very extensive process. It is best to make sure that the goals and the scope of the project are clearly defined before starting.