EPM - Resource Management

0 helpful
1 reply
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.

Please help!! I do not know if the next scenario is possible on EPM. I have one resource who is working in two different rolls with different rates on one project. Do I use her in the one role as a generic resource. I need this quite urgently specific for costing purposes.

Thanks very much.
Joey Posthma
jposthuma@webmail.co.za

1 reply

by tig2

I am not certain what you are asking here. If you have her assigned in two different roles at two different payscales, you can't call her a single generic resource for the purposes of costing. You would have to have the resource track each role individually by time spent thus providing you with accurate costing.

I hope this is helpful!