Discussion Locked

exch 5.5 & outlook 2000

0 helpful
2 replies
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.
in outlook 2000 tasks view no due dates are shown and when in the outlook today view if a task is checked as complete the screen refreshes but the checkbox is blank again and the task is not scored out.Can anyone advise me how to get the due dates to reappear. (The due date is shown on the actual task page correctly)

2 replies

by vinnyd

Sounds like the due date field is missing from the view.

Go to View, Customize Current View, Fields, and add the Due Date.