How to use Gantt and CPM/PERT charts effectively in the development of a project?

6 replies

by mpavankrishna

I am developing a program in VB and Access-95. I am stuck up at a place and I am unable to draw Gantt and PERT/CPM charts to know what is the time when I will be completing my project and what is the estimated cost to complete my project.

by realgem

CPM charts (I call them network diagrams) are useful in planning. They let you show in a diagram the relationships between the tasks and the order that they must be done in.

While you can certainly record/display dependency information using other means, the CPM diagram communicates the information better. I use them especially for "proofing" my schedules, although I find them cumbersome for developing the plan (that might be an artifact of the tool I use, though).

The Gantt chart is not really a planning tool - it's more of a reporting tool. It shows task and time info such as start date, end date, and duration. Better products will let you "roll up" the Gantt to a summary level too.

by robert_hermans

It is unclear to me what you mean with "while developping".

Tools like MSProject and a lot of others provide this Gantt Chart functionality.
I sense that your needs are different, can you explain ?