linking tasks across projects

0 helpful
1 reply
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.

How can i link tasks between projects and how can i handle Projects within Projects

1 reply

by gaspar pacheco

I supposed that you're using MS Project ('98 or 2000)

If so, check this.

"Link tasks between projects"
First, create three project documents "A", "B" and "C" where every one are independent each other.

Second, for each project ("A","B" and "C") create three tasks named x.1 to x.3 where x is the name of the project. Foz expample, project B had tasks B.1, B.2 and B.3. You can put any value at "duration", "start" and "finish" fields.

Third, create a consolidation project named "ABC" with two tasks:
1) the first task is inserted using the follow menu options sequence: Insert + PRoject... + (select file "A.mpp")

2) the next task are created using the same steps changing the selected file by "B.mpp"

Fourth, outline them selecting the first and second tasks recently created and applying
Project + Outline + Show subtasks

Fifth, select tasks "A.2" and "B.3" clicking on it using Ctrl key (as is used to select separated cells on Excel)

Sixth, select this menu option sequence:
Edit + Link tasks.

Now, check the contents on fields "Predecessors" and "Successors" for each task linked.

"Handle project within projects"
First, using the same examples as above ("A.mpp", "B.mpp" and "C.mpp") and keeping opened the"ABC.mpp" file select the task "B.2"

Second, insert the project "C.mpp":
Insert + Project + (select file "C.mpp")

Third, outline it:
Project + Outline + Show subtasks

Watch that project "C" is inside project "B" that, at same time, is inside project "ABC".

------

I hope had helped you.

Sorry for my english.

Bye.