MS Project Server 2003 tasks are missing

0 helpful
3 replies
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.

Three part question:
1. We setup Project Server 2003 and defined resources in it that attached to their email and .Net logins.

Then I published an existing MS project plan to it and used the "Build Team from Enterprise Resources". The team could see their tasks but could only update the "% complete" - and it adjusted the remaining work based on what was entered. How do you let the members of the project enter their HOURS instead of % complete?

2. Because of large scope changes on the project and some slight team member changes, I built a new MS project plan that I saved as "unpublished" until I was done with it. Then I tried to publish it and assign resources like I did the first one. However, when I did the project showed up but the tasks DID NOT SHOW UP for the team members, even though they were matched like before to the Enterprise resources. I tried "Clean Up" link and deleted the old project plan. However, there was no change - still no tasks from the new project plan assigned to resources. I tried making a backup copy and went ahead and removed all actual data from the New Project Plan and tried to publish and assign enterprise resources again. Still no change.

Next will try uninstalling Project Server 2003 and starting over (since it worked the first time)or having people assign themselves to tasks that have their name on it however this is a very tedious process.

3. Another manager just alerted me to the fact that our time has tripled for the project plan, and I wonder if this is because I chose "republish assignments" thinking this would make them visible. I believe I did this about 3 times and I wonder if this is the cause of the triple time change...
Thanks!
Mary

3 replies

by k.boden

Part 1. Was project project effort driven? We enter our projects based on Fixed Work. This allows team members to enter their hours worked as well as hours remaining.

Part 2. It sounds like the tasks were assigned to "resources" rather than "enterprise resources". I have had that experience too when not using the on-line resource pool. One way to fix that is to remove all resources (or create a new project with no resources) then once you're on-line, assign/reassign them from the enterprise resource pool.

3. The triple time is probably due to the doubling up of resources. Just a guess. The republish assignments shouldn't have any effect on the plan no matter how many times it is published.

by furqan asrar

1. You might also want to check the Admin -> Customize Project Web Access link under "Specify the default method for reporting progress on tasks"

2. Instead of Mapping resources, why don't you use "Build Team from Enterprise" and add all the resources before making the Project Plan.. In fact, go to the Resouce Sheet view and check for duplicate resources.

3. Most probably that is not the reason. In fact, I think you might have duplicated the tasks while copying/pasting or the like.. You might want to view the Project on Outline Level1 and see if there are duplications of the whole Project.

by amin

Hi
I planned a project with MSP and assigned tasks to my resources and published the project,but when resource login tp PWA cannot see their tasks!
please help me :(
Thanks