I have some problem while entering the actuals for a task while doing it from the webaccess.
All the fields for the tasks are read only and i could not enter any actual data.can any one tell me what the reason could be?

4 replies

by ansonrah

take a look at settings, specifically whether the file is locked during multiple access. then check to see whether the file is open somewhere else.

by liko

Starting with the basics:
1. For the Timesheet View or Gantt chart view, be sure in the View Options tab that you have selected 'All Outline Levels' to be sure you are seeing tasks assigned to you.
2. You are probably not assigned as the resource on the tasks that are greyed out.
3. Be sure you are trying to enter into the correct columns: Actual Work and Remaining work. Those columns may not be opened up wide enough for you to see them.
4. Also, in order to see 'all' of your tasks you must select All Tasks on the left side pane of your View My Tasks web access page.

by pmqueen

View "tasks" via the timesheet template. This is a split pane. Enter your actual hours in the right pane. It calculates and displays the total actual for that task in the left pane. If you wish to change the remaining work, change it in the left pane. If you wish to log time to a task in the past or future, change to entering hours by day versus by week.

by pmqueen

View "tasks" via the timesheet template. This is a split pane. Enter your actual hours in the right pane. It calculates and displays the total actual for that task in the left pane. If you wish to change the remaining work, change it in the left pane. If you wish to log time to a task in the past or future, change to entering hours by day versus by week.