MS PROJECT WEB ACCESS
I have some problem while entering the actuals for a task while doing it from the webaccess.
All the fields for the tasks are read only and i could not enter any actual data.can any one tell me what the reason could be?
IT Employment
I have some problem while entering the actuals for a task while doing it from the webaccess.
All the fields for the tasks are read only and i could not enter any actual data.can any one tell me what the reason could be?
by ansonrah
by liko
Starting with the basics:
1. For the Timesheet View or Gantt chart view, be sure in the View Options tab that you have selected 'All Outline Levels' to be sure you are seeing tasks assigned to you.
2. You are probably not assigned as the resource on the tasks that are greyed out.
3. Be sure you are trying to enter into the correct columns: Actual Work and Remaining work. Those columns may not be opened up wide enough for you to see them.
4. Also, in order to see 'all' of your tasks you must select All Tasks on the left side pane of your View My Tasks web access page.
by pmqueen
by pmqueen