I want to change a constraint on a task from “Finish Earlier than” to “Start No Earlier Than”.
I have the code, it’s executed without error, but it doesnt change anything.
Is it a bug, possible, or my code is just wrong?
Thank you for answering,
I tried to do it of two different way:
Dim oTask As Task
For Each oTask In ActiveProject.Tasks
SetTaskField Field:=”ConstraintType”,Value:=”Start No Earlier Than”,allSelectedTasks:=False
SetTaskField Field:=”Constraint Date”, Value:=oTask.Start, AllSelectedTasks:=False
Next
OR
Dim iRow As Integer
For iRow = 1 To ActiveProject.Tasks.Count
SelectRow Row:=iRow
SetTaskField Field:=”Constraint Type”, value:=”Start No Earlier Than”, AllSelectedTasks:=False
SetTaskField Field:=”Constraint Date”, Value:=ActiveProject.Tasks.Item(iRow).Start, AllSelectedTasks:=False
Next