Why are the tasks\cells of Mircosoft Professional project plan scrambled after publishing to Mirosoft project server 2003.

1 reply

by faisalmasood

By scrambling of tasks / cells you mean that tasks appear in differnet order in PWA Tasks page than they were in Project Plan, then its the default behaviour. You can sort tasks by clicking on any column in the Tasks page.

You can edit the Timesheet view in Project Server 2003 to add IDcolumn. After that republish your plan. Now go to Tasks page & click on ID column to sort tasks by ID as they appear in Project plan.