We use MS Project 2003 to track medical device engineering projects (software and hardware). Frequently our projects take longer to finish than originally planned due to client scope changes or issues that turn up during the development process.

In our projects there are usually 10-15 tasks that go on until the project finishes, for things such as weekly meetings (Out of usually 100-200 tasks total.)

When the project is extended, the finish dates of those tasks need to be extended and hours added to the scheduled work.

Is there a way to schedule these 15 tasks so that if the project end date changes, the tasks extend automatically? Currently we have to go to each individual task and change the Finish date and add the additional hours.

Thanks for any help!

3 replies

by haris

hi,

You can create these tasks as hammock tasks. A "hammock" task is dependent on external dates for both its start and finish dates and, ultimately, its duration. The name, hammock task, is derived from the way a hammock's shape is determined by the distance between the points to which it is attached.

To build a hammock task between two other tasks, follow these steps: These steps consider as an example three tasks A,B,C; where B is the hammock task and A and C drive the dates of this task. You can apply this to all your hammock tacks.
1. Create or determine three tasks that correspond to A, B, and C.
2. Highlight the cell that contains date A (the date that will determine when task B starts).
3. On the Edit menu, click Copy (Cell).
4. Highlight the cell that contains the Start date for task B (the hammock task).
5. On the Edit menu, click Paste Special, and click Paste Link.
6. Highlight the cell that contains Date C (the date that will determine when task B finishes).
7. On the Edit menu, click Copy (Cell).
8. Click the cell that contains the Finish date for task B (the hammock task).
9. click Edit, click Paste Special, and click Paste Link.

Kind regards,

Haris