I am supposed to run a Project status report every Friday, and let's say, if I forget to print a report (which by default has a title that says as of Status Date)
Now, two days later I want to run the report as if I am running it on Friday (two days ago), I change the in Project Information dialog..(there by it recalculating progress lines..) however, when I run a particular report, the date still shows up as the current date
Is there a way to run a report which is as good as running a report two days ago? (ofcourse, I do not want to change the System date on the machine)
Thanks.

2 replies

by haris

hi,
You cannot use the Status Date in the manner you have described. Project uses the status date to perform earned value calculations, identify the complete-through date in the Update Project dialog box, and place progress lines. When you enter progress as percent complete or actual work to date, Project uses the current date or the status date, if different, to determine where to place actual work and where to schedule remaining work.

You can however create Custom reports. To create a custom report:
1. On the View menu, click Reports.
2. Click Custom, and then click Select.
3. To create a task or resource report, click New in the Custom Reports dialog box, click Task or Resource, and then click OK.

You can print cutom reports wich whatever date you would like to appear in print.

Regards,

Haris.
-------