I am an IT Manager within an NHS Trust. I am about to use a partner to take on the primary contractor role in a project to migrate our existing Novell network to Microsoft NT.

Traditionally, acceptance criteria have been based on meeting specific requirements but I feel this is a high risk method for anything other than a simple discrete project. I'd therefore like to develop acceptance criteria requiring that the delivered product is "fit for business use".

What I don't want is to endup having endless discussions, and possible disagreements, over the interpretation of fitness for business use so I'm looking for guidance from anyone who has relevant experience.

1 reply

by pete_smith

Did this last year.

No point in trying to write a technical spec fot eh acceptance keep it simple and use measures which relate to your users requirements.

We wrote the following:

1. A list of common tasks performed by our users, with timescales on how fast these had to be completed.

Acceptance was multi stage.

Stage 1: included a simulation of 300 users running the common tasks and recording the response times. Done using robot PC's

Stage 2 was : 30 days continuos reliable operation. No part of the network was allowed any outage time for 30 days. If it occurred then it was agreed that the clock would be reset.

Payment was broken into milestones with
30% after Stage 2 completion and a bonus of 30% dependant on the measured satisfaction of all 500 staff affected by the migration.

Tough criteria, many suppliers said how good they were, years of experience etc.. , but they walked away when they were asked to lay their profit margin on the line.....