The purpose of activity-on-node (AON) is to represent relationships (dependencies) between tasks on a project.
The diagram will consist of several nodes (usually boxes), each representing one project task. The box will contain information about that task, such as the name, id, dates, cost, person responsible, etc.
The nodes are connected by lines, representing dependencies. If task B must follow task A, then there will be a line running from task A on the left to task B on the right. Note that arrows are not normally used - flow is implicitly left to right.
Many project management tools like MS Project allow you to create one form of network diagram or another. Some products are good at it, others suck quite badly.
You cannot complete your network diagram until you have identified your tasks and the relationships between them. The network diagram is a good way to graphically represent your project. You can use them as part of the plan development process, and to communicate with stakeholders.
However, they are usually a pain to print and assemble (unless you have a large plotter).