During asset creation, either the purchase order or the accounts payable voucher was going into error status. Ideally they should come together and not be in error. This used to work until a PUM update was performed on the PeopleSoft version.

2 replies

by birdmantd

..... to PeopleSoft ?? Not sure anyone else can resolve this.

by peoplesoftawscloud

I think the interface ID is old and the cap threshold functionality may not enabled in the system. Try studying the process that brings in assets from sub modules to see if there is a step missing. Also, maybe you could locate more recent interface error data and see if the problem is due to any recent PUM updates. If the problem has occurred due to a recent update, a patch can be created and applied to PeopleSoft instances.