5 replies
This is such a broadly scoped activity that I strongly suggest using a consulting company that has done this type of thing before. (I'm not one, but could suggest a company we've used in the past...)
HVAC is dependant upon the type and number of the equipment you expect to run. How high is the raised flooring going to be? What type of fire protection are you going to use?
You need a good idea of how the network is going to be designed, and make sure you have a good cable contractor that will take some time to make sure it's done right. My company has 4 major sites across the US, and the difference in cable contractors used for each site is amazing. Some of the jobs are just awful. They look awful, and the quality is just not there. In other sites its just wonderful. We've begun to fly the best contractors around to other parts of the country to make sure we get the quality we need.
The raised flooring I mentioned above is at least 2 years out in availability. If you are even speculating, get the order in now.
Cabinet layout, power layout, redundant power conciderations, UPS, support personnel and their seating area, to use long range KVM switches or not, and if not how many keyboards, monitors for how many machines, etc. etc. etc.
Structurally, can the building handle it? What about the telecommuncations availability? Can you bring in data circuits from more than one point in the building? How much will a 2nd demarc cost, how long will it take for the LEC to build it? Make sure it originates from a different Central Office.
Again this is such a broad topic, I could go on and on, and already have to some extent. This is definitely something you need help on.
by richcote
by beeba
by richcote
by richcote
This discussion is closed to new replies.
Trending Networks posts
Sort by Trending