Here is my problem:

I want to insert a number of custom cost fields in a task sheet, so that the
individual figures in these fields will be added to the 'Total Costs' Field. Or to word it differently, I want to have more than one 'Fixed Cost' Field operating in the one sheet. I've tried to no avail, so am wondering if this is actually possible.

Thanks in advance....

5 replies

by ksearch

Yes, it is possible. You have a number of empty cost fields (Cost1, Cost2, Cost3, etc.) as well as the ability to create fields that perform mathematical computations in Project 2000.

You will get a much better response to your question by going to the project forum
News server: msnews.microsoft.com
Group: microsoft.public.project2000

good luck! and let us know how you get on.