Function Point Approach (FPA) Estimation

0 helpful
2 replies
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.

Hi,

I would like to know how can an Functional Points counted for Overall Project can be equated with Efforts interms of PMdays ? i.e. How can we equate (n) FPS = (n) PMdays

Is there any relationship? If yes, what is the formula ?

I would appreciate if any one could answer this question.

Thanks,
Srini

2 replies

by connectvb

Hi Srini,

Once you get the no. of adjust FPs, at that time you can increase it by a percentage based on your companies value, we normally, have it anywhere between 8-10%.

If I have misunderstood your question, please explain, so I can share my experience.

by srini_tanla

I appreciate your answer for giving answer to my question.

I know that

Productivity Rate = Efforts in Hr / Size in FP
Delivery Rate = Size in FP / Efforts in Hrs.

but how do i calculate the Productivity without knowning the correct efforts in Hr? can you help me ?

Is that value depends up on the company 's productivity rate ? like you suggested ? or something else?