I want some advice in terms of how to break apart a project in qualitative milestones, while also tracking the progess and budget of each of facets involved in a given project...I have inherited something of a mess in terms of organization and tracking of existing projects...MS Project does not give me what I need..

9 replies

by yatst

I am curious which part MS Project is not providing you since it is capable of tracking seperate projects from one file and capable of tracking to costs of each project and/or (if needed) each milestones cost separately. If you'd like to know how contact me.

by tphurley

This sounds not so much like a tool problem, but one of methodology. The methodology tells you where logical breaks of work should occur and this will give you the points that milestones should fall out of. Methodologies define how you are going to do specific types of tasks and helps to make sure that all the appropriate steps are followed and are repeatable from project to project. I am currently using an IBM WSDDM Methodology, but there are others out there. You need to find one that meets the needs of you organization. TPH :-)

by realgem

Start by defining the ultimate objectives of the project. These MUST be known. Determine what deliverables (perhaps based on a delivery methodology that you have, or just plain made up on your own) you need to produce in order to satisfy the objectives.

Take those deliverables, and break them down further, but keep the results tangible. For example, if one of your deliverables is a system design document, you might get the following deliverables:
- design notes
- draft design
- review meeting minutes
- final draft
- approved copy

Once you're at a satisfactory level of detail (and you're the one that decides this - there is no magic formula), you take the deliverables to the project team to determine the tasks that are necessary to produce the deliverables. Then, they must estimate the tasks.

If you are serious about tracking project costs, then you should have a task for everything that will be done on the project. You define the level of detail, but be considerate to your team. Too many 10 minute tasks will only cause the to fudge the answers.

As for tracking, you should know who worked on which task when, and for how long. This is all the information that you need to drive a good cost / schedule tracking process.

by timp999

I agree with the points brought up by RealGem in the previous post, but want to point out some other considerations for serious cost controland organization.

The process RealGem described is what is known as building a "Work Breakdown Structure" (WBS). The WBS is essential to all other project accounting and metrics. It's the basis of the Project Schedule, It provides you a system to use for tracking costs at each level called a "Code of accounts", and allows you to plan in greater detail asthe project moves forward. A simple WBS would look like this:

1. Project X
1.1 Deliverable A
1.1.1 Bob's Work Package
1.1.2 Ted's Work Package
1.2 Deliverable B
1.2.1 Jane's Work Package
1.2.2 Karen's Work Package

This is the point where you would have your functional leads estimate their effort to accomplish their tasks. As previously pointed out, the level of detail is going to vary, perhaps even within a single project based on things likehaving an inexperienced lead on a work package that you need to micro-manage a bit more, or a really risky package of work that you have to watch closely.

Now that you've divided up the work at the deliverable level, you'll notice that you have yourself a neat little accounting system as well. You can track costs at any level, and roll them up easily. You can also establish a work authorization process that will not allow departments to charge to a work code (1.1.2 for example) without a signed (or otherwise approved) work authorization form. Of course, your accounting systems have to support this.

For more on this topic, I'd visiting http://www.pmi.org and a download of the PMBOK Guide (Project Management Body of Knowledge). A good source for Microsoft project information is the "Microsoft Project Users Group", at http://www.mpug.org.