As more of a survey than a question, I am curious how others perform large scale rollouts or PCs (laptops and desktops).

Specifically I wonder if you:
1. have PC vendors load an OEM image
2. reimage using a Ghost type product
3. use a Desktop Management system (which one)
4. other.

I/we are struggling with what is the best way for our organization to do this.

8 replies

by ckilday

Mark,
Two years ago, our organization migrated from Win95 to NT. We were also upgrading about 1/3 of our PC's. For the new PC's, we had the vendor load a generic NT system with MS Office. We customized that build on-site for company specific applications and then created a ghost image to be used on the units that were going to be re-used...sort of a hand-me-down process as the still serviceable PC's were wiped and then rebuilt using the ghost image. We also had Microsoft's SMS product available, but could not take full advantage of it because a number of our locations are geographically isolated and use satellite connections. You need a "robust" WAN and LAN for SMS pushes on a company-wide basis. So, we also put together a team of technicians and trainers to go to the remote sites and perform the installations there.
The biggest problem we faced was the amount of individualization that had occurred. We worked the users and with upper management to get a standard list ofapplications approved for use on the company PC's and when we rolled out the new units, we removed the ability to load programs onto the PC's from all but the Network admins and Technical support personnel. Two years later, this is still a touchy subject among our former "super-users", but trouble calls are down and are fixed faster as a result. Hope this helps.
- ck

by howley

I have used three methods in the past and which one you use really depends on the environment. I have had the OEM load a template we sent to them. This is good for very large deployments with tight time frames, how ever everyone will get the same computer no special software, and you need to make 120% sure that the template you give the manufacturer is right, I had a deployment team brought to its keese when they had to go back and make changes to all of the computers the day before the rollout. To install special software we used SMS installer (part of Microsoft's SMS) to make a package that the user could execute then had it available to those people on a web site. The packages are fairly easy to create with this tool and there are other tools out there such as, Lannovations Picture Taker which I have tested but never really used.
If your departments are going to have different software needs ghosting or imaging works well. This is nice because it is very easy to make new templates for each department and fairly quick to load. The last method I have used is a scripted install. The nice thing about this is that if done properly it can be updated quickly as peices change, such as the version of software the down side is that it does need someone of some technical knowledge to maintain it and there is a risk that if the person who does that leaves you could lose a lot of the details of how that was set up.

The most important thing to ensure a smooth rollout regardless of the method to get systems on the desk is to have a locked down standard communicated out to the user community. I have seen rollouts sunk by slack standards that changed with the wind, and techs stuck spending cycles going back to desks over and over to get the users new computer just like their old one.

Hope this helps

by jimbb

Hi Mark,

I seem to need more space than I have, so I suppose I'll appear twice here ;-)

Part of our business is doing roll-outs like you need. Our exact part in the whole process depends a bit on what the customer wants, how much knowledge isinternally available, and how much they are willing to spend.
First of all you need a good inventory, of what machines will be kept, how many replaced by which type(s), what software is currently used and so on. The quality of this inventory is vital for the rest of the roll-out, and is often underestimated.

The customer defines an image, and often needs our assistance to fine-tune it. Should certain printer-drivers be in it? Do you want context-menus to be (un)available? Should things like "Windows Update" be removed? Not so much the "standard" install, but little things like that take time and effort.

Once that image is ready it is sent to us for deployment on the new machines (we do test it first), using the method the customer chooses - Ghost or something else. The customer then uses the first batch of finished machines to get some "old" ones back to re-ghost. 99% Of the time the customer "uses" this new purchase to re-ghost everything they intend to keep, and re-standardise everything.

Individual applications are installed using Novell's Application Launcher, a part of ZENworks, and similar to SMS - I work for the Novell department, I'm sure the NT boys will use SMS. Don't underestimate the time needed to develop and double-check those applications. Don't underestimate the work involved, you need to check a lot of files and registry keys, certainly if you choose to use a shapshot-like method.

...

by jimbb

...

Plan carefully. You can't start making or testing your applications before you have a workable image, but you can't start after the image is final either, you may need to incororate drivers or patches.

Don't forget to have a pre-rollout. In this you'll still find small issues that were missed in the lab. And don't forget to document every single step, from a detailed description on how to make an image (you don't want differences because different people did different images), over a description of every application you automatically install, to a post-rollout checklist for the bloke who actually connects the PC at the user's desk.
And don't make your planning too tight, you will need all the flexibility you can get.

Good luck. A well-planned well-prepared rollout looks like a breeze in the user's eyes, and that pays for all the hidden effort.

Jim