Hey all,

I have a problem in shown the assign resource in the PWA or in Outlook
plug-in for MS Project server.

E.g. if I assign a resource type material or work (but as equipment ) how I
can keep track the use of this resource or how the worker (the Human) come to
known this resource is assign with him in the same task.

Another question if I consider some resource as material it is ok, but if I
created the resource as work (but as equipment) MS Project server will create
a login account in PWA authentication type is project server. Is this
considering a used license?! And who will update task which assign to this
resource which actual an equipment?!

note:
i am using project server 2003 + SBS 2003 server + MS Project Pro 2003 ( 1 CAL ) + 3 CAL for PWA