Wondering if anyone has a generic data center equipment move plan that I could revise as necessary to reflect the specifics of my situation. Scope would not include any construction requirements of the new site other than certifying that the required environment (electrical specific to the moved equipment, cooling capacity, etc.) is in place and addressing any identified gaps. This is not a move into virgin space. I'm looking for something that covers the waterfront, including: (1) certifying new site readiness, (2) application systems dependencies, (3) network cutover, (4) move day & go live process, (5) risk assessment and fallback, (6) disaster plan revisions, (7) etc.

13 replies

by trdrm

Tried to download the Guide with a request but I have not received it.

by deadly ernest

that may help you some by giving you a starting point - it is in MS Project and designed for general office moves with capability for expansion to suit specialised needs - it is a few years old and has been used for several general office moves. The file is about 380 kb, email me at ernest@bywater.net.au if you want a copy.

edited to add this update.

www.bywater.net.au
go to the menu item "Downloads"
on that page select the 2nd item labelled "Moving Project File"

NB: This was designed some years ago as a generic file, in Microsoft Project, to assist with moving an Administrative Office. I've used amended versions to move house, as well as a few office shifts.

Please feel free to download, amend, and use as you wish.

I would appreciate being sent a copy of any amended to be more data centre based, so that I can add this to the site.

For the last several months, I've been averaging 2 requests a week for this file. Now it's out there, go get it, if you want it.

Thank you

edited to add web site to title, hopefully this will encourage people to look for it there and get it quicker. If you find it useful and expand it, please send me a copy of the new version.

by deadly ernest

www.bywater.net.au
go to the menu item "Downloads"
on that page select the 2nd item labelled "Moving Project File"

NB: This was designed some years ago as a generic file, in Microsoft Project, to assist with moving an Administrative Office. I've used amended versions to move house, as well as a few office shifts.

Please feel free to download, amend, and use as you wish.

I would appreciate being sent a copy of any amended to be more data centre based, so that I can add this to the site.

For the last several months, I've been averaging 2 requests a week for this file. Now it's out there, go get it, if you want it.

Thank you

by deadly ernest

after I got about 60 requests for it. Change my website hosts about 90 days ago, and just checked the website stats.

Boy am I glad I put this on the web site, I've saved myself a lot of emails. During the last 90 days I've still have five requests for an email copy, but the web site has had 761 people download it from the web site averaging almost 8 and half copies a day.

I wonder, would you people have paid me $5 per copy for it or not, oh well, too late now. But I could've done with the money.

by jcraddock

We may have synergistic interests. I am an independent representative of various interests out of Scottsdale, AZ. I am a commercial hard money broker as well I put deals together in the technology sector.
(pagfunding.com)

I am currently working with a group on the design of two new Level 4 data centers in the Phoenix area and am looking to connect with a major player to colo about 35,000 sq ft.

Construction to be completed within 10-16 months, which means the right client will be given the opportunity to dictate design and recommend facilities. We are looking for a 20 yr. commitment, offering first 3 years free.

-James Craddock Cell: 480-747-7252
email: jcraddock@vigilant1.com or james@pagfunding.com

by ultracoel

hi

Just reading your prost n what a coincidence... Ive been given a similar project... i need to submit a rough copy of my server relocation n was hoping for a few ideas regarding planning...
Is it possible to forward me the guide as i tried to download it but unfortunately get some error while downloading... could you perhaps send it directly to mail...
ultracoel@yahoo.com thanks will appreciate it!!!
Thanks

by lfgarcia

Hi,

I'm working on putting together a data center relocation plan and I was wondering if you ever received the guide you requested? I'm having a problem with the download as well.

Thanks.

by pdbouldin

This can be found in the realm of BICSI. Covers this and more. When I manage data center moves or migrations I start with the apps first, then synch all that up with the inventory of the machines on the floor. At that stage I'm working with the in house Sys admins to plan migrations based on the criticality of the app. Big note on power and cooling. You probably don't need near what you have once the true up is done. Feel free to contact me, Patrick Bouldin, independent consultant at pdb@txit.biz