5 replies
by mslizny
by marabella
Poster rated this answer.
by haris
hi,
There is a report titled "Who Does What" you can use this report. Its accessible by Main Menu->View->Reports.
Another option is to use the resource tracking tab. Click on the resource tracking tab and it will give you the time sheet of everyone. You can print this time sheet either for resources or show the cummulative time.
by kwf777
by projman99
The best way to do what you need to do is to leverage the capabilities within the OLAP reporting functions of Project Server 2002 or 2003 [if you upgrade]. If you don't want to go that route you could certainly develop some InfoPath forms that could include the information/graphics that you need directly from the database.
I am a Project Manager and not a developer but I am very technical and know this can be done.