Hi
Some project tasks extend out to September 2009, but the print preview displays the time bars to June 2009 only; I've adjusted the timescale and zoom, but to no effect; the print preview still shows the bars till June end only.

thanks
Al

2 replies

by alanem

found the problem:
in the print settings adjust the timescale for the desired time range.