With those numbers, you're going to need a high-end tool.
By the way, I'm assuming that you are talking about the project management concepts of project monitoring and project change management, since you've posted this in the PM forum.
High-end tools like Primavera Project Planner and ABT Results Management Suite 5 will do the job. With your numbers, you will have a lot of routine administrative communication (e.g. timesheets, resource assignments), and these two tools automate this work fairly well.
MS Project with MS Project Central may also be able to do the work, although I don't know anybody using MSPC. Also, I'm not sure about MSP's ability to re-baseline after an approved change request.
by ukothari
Try ProjectByNet, details on www.projectbynet.com
Good luck