Project Scope Control

0 helpful
1 reply
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.
Our organization is in the process of adapting a project management methodology for our work environment. We have had a lot of discussion surrounding project scope control. In particular, we have differing opinions on when it is appropriate to change a project baseline. Any rules of thumb or criteria that we might present as discussion to our work group?

1 reply

by ayoshi

If the scope is defined and the budget has been set, then you have the schedule set and the target budget.

If a scope creep is going to affect the project baseline, then you must get one of three things from the project sponsor:
1. Include thisin a follow-on project;
2. Here's more budget and time to get this into this scope;
3. I'm not paying for it!

Hope this helps,