Hi Brian--
From a very broad perspective, here are the 7 questions I start with (and answer by integrating into the monitoring tasks) before working with a client on any OEM transform/cube-build project which will/already require(s) continual monitoring.
1. How many concurrent inputs, if any?
2. What's the mix of CI's? (e.g. b2b partner data, internal, cross operating companies, etc.)
3. Are there custom object outputs to consider?
4. How much data needs processing?
5. What's the anticipated growth of the data?
6. When, Where and How with the pre-transform data be loaded?
7. Are there firewall/hardware issues or other backend processes to consider?
I realize these questions may sound remedial--but these 7 questions (well, really how they get answered) have never failed to point me quickly to the problem arena of the transform process--which is usually why the issue of monitoring post-process definition/implementation crops up!;-)
Aside from my general approach--a more specific question: Does your version of the PowerCube interact with the NoticeCast Agent? (I think Series 7 is the base version for the NoticeCast interplay)
I hope this gives you a jump start!