Hello,
I'm trying to generate a report for my team that breaks down by Team > Resource
> Project > Task. None of the reports in ms project 2003 std provide that,
and I've tried custom reports quite unsuccessfully.
Any feedback would be appreciated!
Thank you!
Magda.

2 replies

by bastiaan.deblieck

Depending on the structure of your file(s)/groups/resoruces select view > task usage or view > resource usage.

Add the column "group". In this way you can make selections based on the group a resource belongs to. Use the autofilter to make the selections. Try the "Group by" under the menu item Project.

View is muc more powerfull than the reports.

Regards,
Bastiaan