Just had Project 2000 installed. All previous project priority types were changed to numeric values. Does anyone know if it is possible to convert back to the old text types (e.g., High, Medium, Low) ?

3 replies

by el flush san

Task and Project priorities (which range from 0-1000 with 1000 being highest and 0 being lowest; 500 is the default) are used to 'optimize' resource levelling and therefore are numeric values.

You might want to customize a text field (that has a value list) to achieve the same aim.

by gnc

Was looking for some VBA code. I did find it in an older TechRepublic email. Thanks anyway.