When creating new tasks in Project Professional the default conditional is being set to “Start no Earlier Than” for each task that is created. This appears to have been triggered after using “Create a New Task” in PWA which automatically uses the “Start No Earlier Than” conditional. I cannot change it back to “As Soon As Possible” as the default. Any thoughts?
Thanks-
Beth