1. How does one avoid Resource over-allocation in an environment where multiple Work Plans are utilised, with one Resource Pool?
2. Is it advisable to have one owner for a Resource Pool, or should it availed to persons responsible for Updating/Creating Work Plans?
3. Is there an easier way of consolidating different Work Plans into a Master Project Plan?

3 replies

by kees.valkenswaard

1. The idea behind a resource pool is to get a warning, as soon there is an over allocation. That is at least how I am using a pool. Automatic levelling could do something. However, I would not advocate that road. If you choose automatic levelling in the Resource levelling window [under tools] a task in a new project will automatically move as soon as you allocate a resource from the pool which would result in over allocation. For most people this would be a surprise. It gives what you want.
2. It is up to you. It seems that Project Central has some goodies for that. I am still trying to get that running.
3. What do you mean by an easier way? Inserting projects into a master project is a rather simple action. It is not needed for the over allocation issue [see 1.] However, it is great once you want to link tasks in different projects. A Gantt chart of a master project is also great and impressive at the wall of your office [plotters are here really helpful]