MSProjct Task Update Not Changing Date ?

0 helpful
7 replies
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.
I'm using MSProject 2000. When I update a task with % complete, it doesn't move the scheduled finish date to reflect the % work remaining from date reporting, e.g. 2 days work remaining should have a date at least 2 days from today. Must I manually adjust the scheduled duration to be shorter overall ?Also, if the scheduled finish is earlier than today, & I report a % work remaining, it doesn't move the scheduled finish out to later than today, which is what realistically will happen. What am I missing ? Expecting "too much" from MSP ?

7 replies

by sridharpandu

No MS Project doesnt need to do that because some project managers would like to determine slippages as part of their metrics collection process, so MS project does not automatically change the dates.

by kostrubr

Thank you for your answer. I thought that slippages were intended to be measured against the baselined dates. I haven't base-lined (didn't really think about doing it). But I do think it is reasonable for MSP to adjust a task's expected finish date based on the new information fed it. To accomdate this, I am now adjusting the duration to make the scheduled finish date state what I believe the finish will become as a result of the new information. Before adjusting duration, I have to set the task to "FIXED WORK" because I am not adding more work, just having either a delay in its original scheduled date, or actually expecting to finish it earlier. Once I adjust the duration I must then adjust the % Complete back to what % of the task I now know to be done. Seems like there ought to be a better way.

by krmorriso

There are several different date fields available in MSProject. Once I'm happy with a schedule I usually create a baseline, then set up a view which shows the 1) Baseline Start/Finish (which would be the original dates entered) 2) the default Start/Finish fields which I rename to Planned Start/Finish) and 3) the Actual Start/Finish.

I find that when I do this the Planned Start/Finish dates will reflect tracking information I enter for a task.

by jacob.havik

I normally go to task usage, there i add 3 new columns : actual work, % work complete and remaining work. You can add the actual work, then the % is automatically adjusted and not the scheduled finish date. However if you adjust the remaining work, then the scheduled finish date will be adjusted.

Hopefully this helps
cheers

jacob havik