There are several different date fields available in MSProject. Once I'm happy with a schedule I usually create a baseline, then set up a view which shows the 1) Baseline Start/Finish (which would be the original dates entered) 2) the default Start/Finish fields which I rename to Planned Start/Finish) and 3) the Actual Start/Finish.
I find that when I do this the Planned Start/Finish dates will reflect tracking information I enter for a task.
by kostrubr
by jacob.havik
I normally go to task usage, there i add 3 new columns : actual work, % work complete and remaining work. You can add the actual work, then the % is automatically adjusted and not the scheduled finish date. However if you adjust the remaining work, then the scheduled finish date will be adjusted.
Hopefully this helps
cheers
jacob havik