Using the Administrator Account, I have setup a project, assign resources and published the project to Project server 2007. The resource cannnot see the Assigned task to them in the MY TAsk. However the task are visible to the Administrator under his My task.
Any suggestions would be helpful.

Thanks

3 replies

by rahh

A resource can't see any tasks assigned to them in My Tasks, if they are set to 'proposed' in the project. In the project schedule go to the resource pool and check the status of the resource. Make sure it is set to 'committed'.