12 replies
One person working one day equals one man day.
Two people working together for one day equals two man days.
Three people working together for one day equals three man days.
Twenty people working together for one day equals twenty man days.
The calculation behind it is simply determining how much time (in days) will be required to complete a project. The project will take "X" amount of TOTAL hours (or days). Five people working on the same project for five days takes twenty five man days to complete.
The same applies for man-months.
by kiyoko
by ferrisa
by kiyoko
by realgem
A man month (I prefer "person month") is the amount of work that one person can do in one month.
It is NOT a duration. It may take several months to apply one man month of work to a job if you only have someone working part-time on that job. Likewise, you can apply one man month of work in a very short period of time if you have several people working on that job.
Man months can be different sizes, depending on the company you work for. Obviously, a company that has a nine-hour work day will be able to apply more effort than a company with only a seven-hour work day.
# man months = ttl hrs worked / normal hrs worked in one month
Notice that even the idea of "month" is not simple. Feb 2003 has 20 working days. Mar 2003 has 21 working days. Jan 2003 had 22. I know this is only a one or two day variation, but it could introduce an error of 5% to 10% in any calculation you do. You may wish to standardize the term month. I typically use 21 days:
365 days per year * (5/7) / 12 = 21.7 working days per month. Factor in statutory holidays, and you are left with about 21 working days per month.
by kiyoko
by d. brinson
by kiyoko
by ananthap
For people working in the indusrial environment, a man-month is pretty well defined by some sort of agreement or custom. This is used in all person related costing. In the case of my company, it equals 208 hours. The reasoning is:
8 hr day (man day) x 6 day week = 48 hrs / week.
So 48 x 52 hrs / year.
So 48 x 52 / 12 = 208 hrs per month.
Another company I know of (into consulting) does a 40 hr week and their terms specify only a 40 hour week - with flexitime and transparency in reckoning 40 hrs / week.
For them a man month would be probably be 175 hrs and a man day would have no meaing.
So you see, you can frame it - both with your customers and employees. Be consistent.
End