My interest is to come up with a methodology to bill back processing resources such as servers, DASD, and network products.If any of you have done this, I would appreciate your input. My intent is to baseline it on measurable business terms such as account volumes. What has worked for you?

3 replies

by ga-pilot

We have tried a variety of scheme's with mixed results, for internal ITD Cost recovery.

A pure DASD base rate does not recover the cost fo the hardware in a reasonable period.

I believe a monthly rate to be the best basis. From there, you can decide on the amount, and then use a multiplier for services you may offer, i.e. R&D, Performance, or UAT Services may have different multipliers to cover server differences and software associated with the servers.

Personal observation, customerswill not like any price you set, no mater how small and reasonable it may be.

by teburlew

A way to keep your capital costs down is to lease your equipment with a purchase or upgrade option at the end of say three years. This way, you share the risks, keep your operating costs down, and in most cases charge accordingly while receiving a reasonable EVA (Economic Value Add).

by mike_phelps

George,

I need to put together an Enterprise IS Capacity Planning Project Plan. Do you have anything like this? Are you aware of any good seminars on this subject I could attend.

My e-mail address is mike_phelps@kindredhealthcare.com

Thanks.
Mike