Question Locked
0 helpful
2 replies
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.
Hello, I have a Project Plan and am trying to edit the fixed duration of a summary task. Any suggestions on how to do this?
2 replies
by mtyson79 Accepted solution
Clarifications
by ic-it Accepted solution
This was copied from a tip page.
Tip: Try and assign resources at the detail task level as the summary tasks will total the hours and costs for you. Summary tasks have a default fixed duration task type that you can not change and therefore work and cost will be calculated off the total sum of duration driven by the detail tasks. The duration of the summary task will continue to change as the details change and therefore automatically recalculate the work and costs.
This discussion is closed to new replies.
Trending Desktop posts
Sort by Trending
Question
Floppy drive wont work on my 486
0 helpful
1 reply
Discussion
How to make light speed agent go away
0 helpful
4 replies
0 helpful
1 reply
Discussion Locked
Ryzen 7 7700
0 helpful
2 replies
Question Locked
Issue fully resetting my PC
0 helpful
4 replies