I am looking for help or examples on writing a project VBA application that would do the flowing:

I need to take the Resource Time Scaled data from the BaselineWork fields and copy/move it into the Resource Time Scaled data of the Work filed. Yes, just the opposite of saving the Baseline function in project. I have used the ?TimeScaleData? Method to get the data from the BaselineWork filed, but I do not understand how to get those values into the Work fields. Also I need to do this for ALL resource in the project from a specific start and end date. Any help or examples would be great. Thanks Dave Richter