We do it in the form of KPIs(key performance measurement indices) at the Asia Pac level. Below is a brief on that, hope you find it interesting:
-------------------------------------------------
PROCESSES
Apply and practice project managementprinciples to manage IT initiative/s and support existing systems.
OUTPUTS
Publish IT monthly highlights incorporating the performance measure indices.
PERFORMANCE MEASURE
A. Project Performance
Index to measure percentage of completed projects having met objectives, on time & within budget compared to the baseline or approved changes to baseline.
B. Audit Compliance
Measure the number of Audit observations and recommendations.
Determine data and track KPIs
A.Project Performance
Index:
Actual cost incurred x Actual time spent x 100
-------------------- ----------------
Baseline cost Baseline time
Targeted index value in the range of 0.95 to 1.05
It is suggested that cost includes capital purchases, other general expense (like travel, etc) and external manpower cost incurred by the project. However, individual countries may adopt their respective cost definition standards. Time includes hours budgeted /spent by IT resources for the project.
Plan, estimate & track for projects involving person-days of 10 or more. Report the statistics for index tracking in monthly highlights as follows:
-Project Detail
-Budgeted/Revised Cost
-Actual cost
-Budgeted/Revised Time
-Actual time
-Target completion schedule
Upon project completion, compute and report the index in monthly highlights & the designated document titled – “IT KPI 2002”under project section of Asia Pacific Knowledgebase.
B. Audit Compliance
To minimize the number of Audit recommendation/s, the target being zero
-------------------------------------------------