By trevor.may ·
When creating a calendar; example 12 hour day, 08:00 - 21:00; specific number of days (20), I am finding that when that calendar is added to a project the overall timescale is wrong when duration is in days. However when the duration is in hours the result is correct in date value and end time is 21:00.

In my experience; a user of 12 years there should be no difference in the result whether days or hours are selected. Your assistance in this matter would be greatly appreciated by myself and particularly by my superior