Could someone please help me solve my problem.

I have a master project plan (MS Project 2000) that I want my resources to log in their times against the task(s). However, my company has a separate time tracking software that the resources must use to enter their times. My company would not allow me to make the resources enter their hours in two separate places.

I need the hours to be in MS project for resource managing purpose. Thus, right now I'm forced to get the data in text format from the time tracking software and manually enter them into MS Project to get the Actual Hours.

Does anyone know any macro of how to import the data from the text file and put it into MS Project? This macro would have to associate the resourcename to a particular task.