Help! I have been brought in create views that give the following information in weekly increments:
# of cumulative tasks planned for all projects vs. # of cumulative tasks completed

Is there a way to modify the OLAP cube to reflect time in weeks instead of years, quarters, months, and days?

Thanks!!!

1 reply

by mslizny

If you are using MS PROject, you want to choose View, Reports and create a custom report. Use the report that is the closest to what you want, make a copy and then you can customize it by adjusting the time periods and other elements.