EPM - Resource Management

By joey.posthuma ·
Please help!! I do not know if the next scenario is possible on EPM. I have one resource who is working in two different rolls with different rates on one project. Do I use her in the one role as a generic resource. I need this quite urgently specific for costing purposes.

Thanks very much.
Joey Posthma
jposthuma@webmail.co.za

This conversation is currently closed to new comments.

1 total post (Page 1 of 1)  
| Thread display: Collapse - | Expand +

All Comments

Collapse -

by Tig2 In reply to EPM - Resource Management

I am not certain what you are asking here. If you have her assigned in two different roles at two different payscales, you can't call her a single generic resource for the purposes of costing. You would have to have the resource track each role individually by time spent thus providing you with accurate costing.

I hope this is helpful!