Question

Locked

How do I edit Fixed duration?

By mtyson79 ·
Hello, I have a Project Plan and am trying to edit the fixed duration of a summary task. Any suggestions on how to do this?

This conversation is currently closed to new comments.

2 total posts (Page 1 of 1)  
| Thread display: Collapse - | Expand +

All Answers

Collapse -

I don't think you can

by IC-IT In reply to How do I edit Fixed durat ...

This was copied from a tip page.

Tip: Try and assign resources at the detail task level as the summary tasks will total the hours and costs for you. Summary tasks have a default fixed duration task type that you can not change and therefore work and cost will be calculated off the total sum of duration driven by the detail tasks. The duration of the summary task will continue to change as the details change and therefore automatically recalculate the work and costs.