Question

Locked

How to enter just 2h of work per day per resource in MSProject?

By marijana3006 ·
I am running Project 2007 and need to split 10h of work in 5 days for one resource. A unit for resource is set to 25%.
However, when I force duration, dates do change (two consecutive days), if I put 5 day difference for start and finish, duration changes...
I tried with changing Task type: fixed duration, units, work but it does not make any difference.
I tried with selecting manual calculation in Tools/Options/Calculation but without any result.
Does somebody maybe know where do I make mistake(s)?
Thanks