How can I setup a calendar for a resource that has a strange shift:
eg
Start of shift 11:00 to 03:00 then a meal break from 03:00 till 03:30 and then works from 03:30 till 08:00

When I set it in project it says that the end of the shift must occur after the beginning. However at a mine site that works three rotating shifts one of these shifts (dog watch) works these hours. I'm stuck with project 98.

This conversation is currently closed to new comments.

Thread display: Collapse - | Expand +

All Comments

Collapse -

MS Project

by wedwards In reply to MS Project

I am guessing from your description, that the shift is
11pm to 8am with a break at 3am

Try this:
1> On the Resource sheet, set the Base Calendar to 24 hours for this resource
2> edit the resource calendar and enter the times below:
12:00am to 3:00am
3:30am to 8:00am
11:00pm to 12:00am

MS Project 98 took this for me. Technically the resource's normal shift extends over 2 days. His Tuesday shift actually starts on Monday night.

Hope this helps.

Collapse -

MS Project

by ielectro In reply to MS Project

Poster rated this answer

Collapse -

MS Project

by ielectro In reply to MS Project

This question was closed by the author

Related Discussions

Related Forums