If you're asking for technical help, please be sure to include all your system info, including operating system, model number, and any other specifics related to the problem. Also please exercise your best judgment when posting in the forums--revealing personal information such as your e-mail address, telephone number, and address is not recommended.
MS Project remaining work incorrect
There is only one assignment on the task which shows 88MD Remaining work while the Remaining work on the task shows 40MD
calculation is set Automatic, levelling is set to manual
has somebody had the same problem and found a solution for it ??