MS Project remaining work incorrect

By marcbaetens ·
I'm using MS Project 2007 on Windows 7. I have a plan with a number of activities in fixed duration. when analysing the task usage view, it appears as if the "Remaining Work" of the assignments is not matching the total "Remaining work" on the task.

There is only one assignment on the task which shows 88MD Remaining work while the Remaining work on the task shows 40MD

calculation is set Automatic, levelling is set to manual


has somebody had the same problem and found a solution for it ??