RUP

By c.vijayalakshmi ·
What are the matrices collected in the development phase of the project using RUP

This conversation is currently closed to new comments.

3 total posts (Page 1 of 1)  
| Thread display: Collapse - | Expand +

All Comments

Collapse -

RUP

by md_hashim In reply to RUP

Checking out http://www.isk.kth.se/~anca/6B3016/ProjGenDescr.html could help...

Collapse -

RUP

by c.vijayalakshmi In reply to RUP

Poster rated this answer

Collapse -

RUP

by SridharPandu In reply to RUP

few of them are
1. Time taken to implement (thats the word for development in RUP) a use case
2. Time taken to unit test a use case
3. Time taken to prepare/review the software arch. document
4. Time taken to prepare/review the integration buildplan