how to configure custom field graphical indicators for PWA

by jasmith8242 . Updated 16 years, 8 months ago

Custom field graphical indicators do not appear in PWA

I want to include a task status indicator in PWA. I created a custom field in Project Pro to display graphical indicators that was added to Enterprise.

Tools | Customize | Fields
Selected Field: Task; Type: Duration
Renamed Duration 1 to Jeff Status (Duration)
Setup the graphical indicators
Added a formula: = [Finish Variance]

Confirmed that the field was added to Project Server. (Server Settings | Custom Enterprise Fields | Jeff Status (Duration 1))

The indicators appear fine when added to a project in Professional. They do not appear correctly when added to PWA: My Tasks view.

A column named ?Duration1? is present and ?(Jeff Status)? appears in the column at a summary task level. Green, yellow and red indicators do not appear.

What am I missing?

Thank you,