Question Locked

Project Server 2007 Timesheet Connectivity error

0 helpful
3 replies
Closed to new repliesThis discussion is closed. It stays readable, but it takes no new replies.

I can't complete and submit timesheets to payroll nor maintain accurate progress on tasks due to the following issue:

In PWA2007, after adding or deleting a line in a timesheet that comes from a
project plan and clicking 'Save', I get the error "While communicating with
the Project Server an error occured. Check connectivity with your
administrator to determine if further action is necessary".

The changes made to the timesheet are then lost.

The same problem does not occur when lines which are not from a project plan.

How do I resolve this issue or work around it?

3 replies

by secretariatprojects

I have a user experiencing the same issue as cmperez. The difference being that this users timesheet is not loading with the proper pre-populated tasks and he is receiving the connectivity error message when he clicks on the "Add Lines" button. I've checked all server settings and they appear normal.

by secretariatprojects

So, in our case this is what was prompting the connectivity error.

The user was first deleting out all timesheet lines and then attempting to add new lines to the timesheet. The deletion of all timesheet lines appears to be what was causing the connectivity error.

This discussion is closed to new replies.